WorkHours and NetWorkHours are analogous to WorkDays and NetWorkDays except that they compute time in terms of hours taking into effect the gaps caused by non-shift hours, weekend and holidays.
The syntax for the functions are:
WorkHours
WorkHours (Start Date/Time, Number of Hours, Shift Start, Shift End, [Holidays]).
- Start Time is the date/time start of the task,
- Number of hours is the time the tasks is estimated to take
- Start Shift is the shift start time
- End Shift is the shift end time
- Holidays is an optional argument that points to a range of dates containing the holidays
The function returns the completion date/time.
NetWorkHours
NetWorkHours(Start Shift, End Shift, Start Date/Time, End Date/Time, [Holidays])
- Start Shift is the shift start time
- End Shift is the shift end time
- Start Time is the date/time start of the task
- End Time is the date/time of task completion
- Holidays is an optional argument that points to a range of dates containing the holidays.
The function contains the number of hours to complete the task.
![]()