Dear experts,
Thank you for your time in reading my post, I have an interesting problem I am currently facing and having searched this forum for days I cannot seem to find the solution to my specific problem. Here is what I want to achieve step by step using a one or two buttoned macro:
1. Copy all the tasks for a project plan () into the excel sheet and delete all items such as the first blank column (column a), the free slack and total slack (column G and H). To tell you the truth if it makes it easier I can do this manually.
2. Calculate today's date
3. Compare today's date with the due date and give the following:
- give the number of days to the due date, if the due date has passed can give a minus number, for example, if we take todays date as 12th July if there is a task for 13th july the number of days will be 1, if the due date is 11th July number of days will be -1
- colour them accordingly, so if a due date has passed show as red, if witihn 10 days show as amber and if past 10 days show as green
- If a task is percentage has been updated to 100% (complete) then show status as complete and in blue
4. I would just like the one button which can show display the above. Please can you help with your macro expertise on the above.
5. Would also like another function to do the following:
- If a task is at 0% show as not - started and red
- if a task has a percentage of between 1% - 99% show as in progress and yellow
- if a task has a percentage of 100% show as completed and green, but if it is completed beyond the due date flag in blue
I hope my problem is understood. Please find below an example of the sheet and columns so can create the macro accordin
2 Process & BCP Preparation 15% 260 days 2/20/2012 2/26/2013 100 days 100 days
2.1 Process Documentation Phase 1B1 / 1C1 - Private Bank 34% 130 days 2/20/2012 8/17/2012 230 days 230 days
2.1.1 New PvB Secs Processes Documented 100% 40 days 2/20/2012 4/13/2012 0 days 0 days
2.1.2 BCP Processes Documented 20% 40 days 6/8/2012 8/2/2012 241 days 241 days
2.1.3 Alignment of functions, enquiries and reports with E2E process 100% 30 days 4/16/2012 5/25/2012 0 days 0 days
Many thanks in advance for all your help and let me know if you have any ideas and if you require any further information.
Kind Regards,
Kirpal