Calculate end date

  1. #1
    Forum Contributor
    Join Date
    12-02-2008
    Location
    Brisbane
    MS-Off Ver
    2016
    Posts
    811

    Calculate end date

    I am scheduling a project in Excel - if I have the start date and the number of days effort required to complete a task, how do I calculate the end date ignoring all weekends?
    Last edited by BRISBANEBOB; 10-14-2011 at 06:21 PM.

  2. #2
    Forum Expert daddylonglegs's Avatar
    Join Date
    01-14-2006
    Location
    England
    MS-Off Ver
    Microsoft 365
    Posts
    14,719

    Re: Calculate end date

    Try WORKDAY function

    =WORKDAY(A1,B1)

    where A1 is start date and B1 number of days
    Audere est facere

  3. #3
    Forum Moderator alansidman's Avatar
    Join Date
    02-02-2010
    Location
    Steamboat Springs, CO
    MS-Off Ver
    MS Office 365 insider Version 2505 Win 11
    Posts
    24,733

    Re: Calculate end date

    Try the =Workday function in Excel
    Alan עַם יִשְׂרָאֵל חַי


    Change an Ugly Report with Power Query
    Database Normalization
    Complete Guide to Power Query
    Man's Mind Stretched to New Dimensions Never Returns to Its Original Form

  4. #4
    Forum Contributor
    Join Date
    12-02-2008
    Location
    Brisbane
    MS-Off Ver
    2016
    Posts
    811

    Re: Calculate end date

    Thanks - appreciated

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1