I am scheduling a project in Excel - if I have the start date and the number of days effort required to complete a task, how do I calculate the end date ignoring all weekends?
I am scheduling a project in Excel - if I have the start date and the number of days effort required to complete a task, how do I calculate the end date ignoring all weekends?
Last edited by BRISBANEBOB; 10-14-2011 at 06:21 PM.
Try WORKDAY function
=WORKDAY(A1,B1)
where A1 is start date and B1 number of days