I'm really interested in the accuracy for delivering on time, thus my focus has been on the target date (when I said I would deliver) vs. the complete date (the date I did deliver). Here is more detail:
For example, if the Target column date was 03/31/11 and the Complete
column date 03/31/11, then the Metric column would read as "1.00". If
the Complete column was any date sooner than the Target date, the
Metric would be higher than "1.00"; for a Complete date later than the
Target date, such as 04/06/2011, then the Metric would be under than
"1.00"
Target = K4 (mm/dd/yy)
Complete = L4 (mm/dd/yy)
Metric = M4 (0.00%)
NOTE: My metrics have been provided to me, now I'm trying to determine how to capture that information. Perhaps I need to adjust my approach. I've attached a partial screenshot of my spreadsheet.
Bookmarks