Originally Posted by
sanlen
Instead of the default background color (Grey), and after the status i change to Yes, i want the color for PROJECT 2 & PROJECT3 at MS03 to be changed to Yellow.
In which case
'Gantt Chart'!B3:
=AND('Main Data'!C3<TODAY(),ISNUMBER('Main Data'!C3))*(1+AND('Main Data'!$B3="YES",'Main Data'!D3=""))
copied across matrix B3:K13
same rules as before ... ie one where value = 1 (blue) and another where value = 2 (yellow)
(the only difference in the above formula from before is that now only the last milestone on the project will be flagged yellow [where problem exists])