+ Reply to Thread
Results 1 to 8 of 8

Calculate Work Days Based on Hours Worked

  1. #1
    Forum Contributor
    Join Date
    12-13-2007
    Posts
    138

    Calculate Work Days Based on Hours Worked

    Hey everyone. I am working on a resource model where I need to calculate cost variance based on actuals versus forecasted cost. The issue I have is that the resources are paid on a day rate and the spreadsheet is based on hours.

    For example:

    [Col A - Name] "John Smith" [Col B - Daily Rate] "£200" [Col C - Forecasted Hours] "15.0" [Col D - Actual Hours] "23.0".

    Now in columns E and F I need to work out both forecasted cost and actual cost based on that information. The parameters are that each work day is based on 7.5 hours and there is no overtime taken into consideration. So even if someone works 10 hours, they will be paid only for the equivalent of one day's work (7.5 hours). If someone has worked 15 hours then its 2 days and so on.
    Last edited by FM1; 02-09-2009 at 07:29 AM.

  2. #2
    Forum Contributor
    Join Date
    12-03-2008
    Location
    Cardiff
    MS-Off Ver
    2003
    Posts
    123

    Re: Calculate Work Days Based on Hours Worked

    I have added a column that calculates the hourly rate, and then maade the calculations accordingly.

    Is this what you are looking for?
    Attached Files Attached Files

  3. #3
    Forum Contributor
    Join Date
    12-13-2007
    Posts
    138

    Re: Calculate Work Days Based on Hours Worked

    Quote Originally Posted by Back2Basics View Post
    I have added a column that calculates the hourly rate, and then maade the calculations accordingly.

    Is this what you are looking for?
    Unfortunately not. The issue with that is that the calculations assumes that the resources are paid on an hourly rate which they arent. All resources are paid a daily rate regardless of the hours they have worked. So if someone gets paid £200 pounds a day (based on a 7.5 hour day) and works 10 hours for the entire day, they will only get paid the £200.

  4. #4
    Forum Guru DonkeyOte's Avatar
    Join Date
    10-22-2008
    Location
    Northumberland, UK
    MS-Off Ver
    O365
    Posts
    21,535

    Re: Calculate Work Days Based on Hours Worked

    Re: normalised / non-normalised

    You can't achieve what you want without breaking out the hours by day.... it's impossible to take say 37.5 hours and determine as to whether or not that's 5 days or 4 days + OT.

  5. #5
    Forum Contributor
    Join Date
    12-13-2007
    Posts
    138

    Re: Calculate Work Days Based on Hours Worked

    Quote Originally Posted by DonkeyOte View Post
    Re: normalised / non-normalised

    You can't achieve what you want without breaking out the hours by day.... it's impossible to take say 37.5 hours and determine as to whether or not that's 5 days or 4 days + OT.
    Good point. Im going to have to think of another way around this.

    Mods - feel free to close this thread as what Im wanting to achieve is not really possible.

    Thanks.

  6. #6
    Forum Contributor
    Join Date
    12-03-2008
    Location
    Cardiff
    MS-Off Ver
    2003
    Posts
    123

    Re: Calculate Work Days Based on Hours Worked

    Is this something like what you are looking for?

    I have made two columns for calculating the number of days forcasted and actual days worked. The costs are then generated using these values.

    I have added some conditional formatting so that when the actual costs are greater than the forcast costs the text is red.

    Is this the kind of thing that you are expecting to acheive?
    Attached Files Attached Files

  7. #7
    Forum Guru DonkeyOte's Avatar
    Join Date
    10-22-2008
    Location
    Northumberland, UK
    MS-Off Ver
    O365
    Posts
    21,535

    Re: Calculate Work Days Based on Hours Worked

    B2B, per the OP there is no way to provide a solution based on the sample data given there is no way to calculate the actual costs based on the fact that the organisation is working on a non-normalised basis.

    So if you use the example of 37.5 hours -- without knowing how those hours are broken down at a daily level it is impossible to compute the cost to the employer... for ex. the cost could be as simple as 5 days (each of 7.5 hrs), however, it's equally possible that the employee in question worked 10 hours Mon-Wed and 7.5 hrs on Thursday... therefore cost to employer on a non-normalised basis is 4 days (10 + 10 + 10 + 7.5) .. the OT worked Mon-Wed is irrelevant in calculating cost. Thus without breaking out the work by day it is impossible to calculate actual costs... forecast costs could be calculated if you assume 7.5 hr day constant but not actuals.

  8. #8
    Forum Contributor
    Join Date
    12-03-2008
    Location
    Cardiff
    MS-Off Ver
    2003
    Posts
    123

    Re: Calculate Work Days Based on Hours Worked

    I know what you are saying DonkeyOte, it is impossible to know who the hours are split up over the agreed working days - however I would have thought that it 37.5 hours are scheduled and 37.5 hours are worked, it would be unreasonable to only pay the employee for 4 days work, if 5 are forecast.

    There are other obvious flaws in the spreadsheet that i have suggested - I just wanted to offer a solution for the time being, until FM1 has figured out how he is going to fix the issue.

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1