    Date Calculation

    Hello. Can someone please help me?

    I have a Start Date, (14-Mar-08 for example), and I want to calculate an estimated End Date.

    In a separate form, the user has calculated a number of Days, based on how long the user estimates it will take to do a series of tasks.

    So, we have a Start Date, and a number of Days, (5 Days for example). How can I get an End Date to auto-populate where the End Date is the Start Date plus the number of Days estimated.

    So in my example: 14-Mar-08 + 5 Days.

    Thanks a ton,
    Jon Hook

  2. #2
    Forum Expert daddylonglegs's Avatar
    Join Date
    01-14-2006
    Location
    England
    MS-Off Ver
    Microsoft 365
    Posts
    14,719
    You can just add the two, if date is in A1 and number of days to add in B1 then use this formula in C1

    =A1+B1

  3. #3
    Registered User
    Join Date
    07-02-2007
    Posts
    10
    I think my problem is that my "Days" value is just a number.

    When I try to format that cell, I don't see a way to logically save that value as "Days".

    So my current set-up is: A1 = Date, B1 = Number, C1 = Formula of (Date + Number). That isn't right, is it?

  4. #4
    Registered User
    Join Date
    07-02-2007
    Posts
    10
    Got it!

    Thank you. I tried your suggestion once, and it didn't work. I fooled with it for a bit, and now it is working.

    Thanks a ton,
    Jon

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1