how do i make a date change automatically if i change one before .

Hybrid View

  1. #1
    dpl7579
    Guest

    how do i make a date change automatically if i change one before .

    I have a production schedule within an excel document. I have a start date
    and a release date. Between these dates I have different dates that
    represent deliverys, approvals and review dates. These dates are sometimes
    changed due to weather, client issues, etc. Everytime I have to change a
    date, I have to look at a calendar and make the changes in each cell after
    the first change.

    Is there a way to format all the cells after the first start date, so if I
    change one date, all dates after that will change the same amount of days,
    leaving out weekends and national holidays.

    Take into consideration that the dates listed are not in order. I.e. (Start
    Date 1/17, send 1st round layouts 1/21, get client approval 1/24, etc)

    Any help would be appriciated. Cheers.

  2. #2
    Abi
    Guest

    RE: how do i make a date change automatically if i change one before .

    Do you have a specific time period in which to do everything? I mean, If
    your flow is Start>Review>Approve>Ship (as an example) do you have a set
    number of days that are required between each, as in:

    Start to Review - 10 days
    Review to Approve - 10 days
    Approve to Ship - 10 days

    Or, is there no set schedule, (or at the very least, a policy-driven
    schedule!)

    Abi

    "dpl7579" wrote:

    > I have a production schedule within an excel document. I have a start date
    > and a release date. Between these dates I have different dates that
    > represent deliverys, approvals and review dates. These dates are sometimes
    > changed due to weather, client issues, etc. Everytime I have to change a
    > date, I have to look at a calendar and make the changes in each cell after
    > the first change.
    >
    > Is there a way to format all the cells after the first start date, so if I
    > change one date, all dates after that will change the same amount of days,
    > leaving out weekends and national holidays.
    >
    > Take into consideration that the dates listed are not in order. I.e. (Start
    > Date 1/17, send 1st round layouts 1/21, get client approval 1/24, etc)
    >
    > Any help would be appriciated. Cheers.


+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1