Greetings everyone, I will try to explain my current situation, I have provided a copy of my current working sheet.
As you open the Sheet you will notice 3 charts, each feed of each one, my problem is the dates will not correspond with the days , I started working it but can?t figure out why it won?t automate the current calendar days
1-Chart 1, Feeds of Chart 2, according to the dates requested, for example # 94 is highlighted, the current date for the Quarterly review is 22/24 May, this should reflect on Chart-1 with the current 5 day work week, leading to the Meeting itself.
2- Chart 2, this is the Master Chart, changing the date on LYS, will automatically change the dates on Chart 1 and 3.
3-Chart 3, will give you an outlook of what time frame each milestone and the dates of those items need to be due by.
Needing support on my current situation, any help will be greatly appreciated, Stay Safe