How can I get the result to give me % of work complete, and once the remaining hours are Zero, how can the Work complete = 100%
Cell C3 = 4 hrs
Cell D3 = 1 hrs
Cell E3 = %work complete ?
Attached is my sample sheet
How can I get the result to give me % of work complete, and once the remaining hours are Zero, how can the Work complete = 100%
Cell C3 = 4 hrs
Cell D3 = 1 hrs
Cell E3 = %work complete ?
Attached is my sample sheet
Oceans Blue
Hi Ocean Blue,
See if the attached gives what you want. If more hours are worked after 100% complete, what do you want it to do?
One test is worth a thousand opinions.
Click the * Add Reputation below to say thanks.
Maybe this is what you are looking for:
Enter in E2 format as % and fill down:
Formula:![]()
Please Login or Register to view this content.
A B C D E 1 Start Finish Work Remaining Work % Work Complete 2 01/09/2015 06/10/2015 56 hrs 56 hrs 0.00% 3 04/09/2015 02/09/2015 4 hrs 1 hrs 75.00% 4 04/09/2015 04/09/2015 4 hrs 1 hrs 75.00% 5 04/09/2015 07/09/2015 4 hrs 1 hrs 75.00% 6 04/09/2015 07/09/2015 4 hrs 1 hrs 75.00% 7 22/09/2015 25/09/2015 16 hrs 7 hrs 56.25% 8 01/10/2015 02/10/2015 8 hrs 6 hrs 25.00% 9 02/10/2015 05/10/2015 8 hrs 6 hrs 25.00% 10 05/10/2015 06/10/2015 8 hrs 6 hrs 25.00%
<---------If you like someone's answer, click the star to the left of one of their posts to give them a reputation point for that answer.Ron W
Thank you for the feedback.
If that takes care of your original question, please select Thread Tools from the menu link above and mark this thread as SOLVED. Thanks.
There are currently 1 users browsing this thread. (0 members and 1 guests)
Bookmarks