hey every one
i have one sheet ( attached ) with 10 activities each activity has date EX :
1.1 act1 start in 2-feb finish in 6-feb
1.2 act2 start in 4-feb finish in 7-feb
1.3 act3 start in 5-feb finish in 9 feb
these activities should be related by start to start ( this mean the activities will start in same date ) which i made and it's working
but when i try to related these activites by finish to start ( this mean ex : if 1.2 is f.s with 1.1 the start date of activity 1.2 should be the end date of activity 1.1 , if 1.3 is f.s with 1.2 this mean the start date of 1.3 activity is the end date of 1.2 activity and so on
but it's working![]()
can some one have a look on the attached sheet plz i put arrows in the cells where the prob is .
thanks guys