so would that be based on total days, ie Application 1 start 1/14/2013 end 2/22/2013 is 17 days in jan and 22 days in feb so 39 days total which would be 17/39 of the 10000 attributed to Jan and 22/39 attributed to feb?
so would that be based on total days, ie Application 1 start 1/14/2013 end 2/22/2013 is 17 days in jan and 22 days in feb so 39 days total which would be 17/39 of the 10000 attributed to Jan and 22/39 attributed to feb?