Splitting out a cost by date

  1. #1
    Registered User
    Join Date
    05-16-2013
    Location
    England
    MS-Off Ver
    Excel 2007
    Posts
    2

    Splitting out a cost by date

    Hi there,

    First post.

    I am creating a cost tool. Currently the costs are divided into categories by supplier (IT Supplier 1, IT Supplier 2 etc. along the X axis.) Along the Y axis I then have date ranges i.e. 12/1/13 - 15/6/13. Is there a way excel can take the cost per IT Supplier and split it across the date range by month?

    Thanks,
    Andy

  2. #2
    Valued Forum Contributor
    Join Date
    10-26-2008
    Location
    Birmingham, UK
    MS-Off Ver
    All versions up to 2010
    Posts
    1,025

    Re: Splitting out a cost by date

    Can you share with us a before and after example which will help us to help you.
    Thanks
    Tony

  3. #3
    Forum Expert
    Join Date
    08-12-2012
    Location
    Sydney, Australia
    MS-Off Ver
    Excel 2010
    Posts
    5,636

    Re: Splitting out a cost by date

    Hi Andy

    Doesn't sound too complicated
    To have better idea of what you want
    are you able to supplier a sample file data along with expected results

  4. #4
    Registered User
    Join Date
    05-16-2013
    Location
    England
    MS-Off Ver
    Excel 2007
    Posts
    2

    Re: Splitting out a cost by date

    Test - spread cost over a given date range.xlsx

    Attached

    The plan is to have Sheet 2 showing the spread of cost broken down by Supplier and date range. The date ranges come from Sheet 1.

    Andy

  5. #5
    Forum Expert
    Join Date
    08-12-2012
    Location
    Sydney, Australia
    MS-Off Ver
    Excel 2010
    Posts
    5,636

    Re: Splitting out a cost by date

    sorry gave it a crack, a bit beyond my level
    More complicated then i imagined
    at most i can get the calculation for working days in month but that's with "alot" of extra data entry on the side already
    even then i still not calculating the "edge" (start and finish) months correctly

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1