calculating values over dates

  1. #1
    Registered User
    Join Date
    06-09-2011
    Location
    North Carolina, USA
    MS-Off Ver
    Excel 2007
    Posts
    13

    calculating values over dates

    Hello,

    I have the following problem: I have production runs over time at different rates and different grade of product. I am trying to see how much of which is produced each month but can not come up with something easy. Any help would be a plus!

    Let me show an example:

    Run 1:
    Start: November 1
    End: November 15
    Grade: A
    Daily Rate: 500

    Run 2:
    Start: November 16
    End: November 25
    Grade: B
    Daily rate: 430

    Run 3:
    Start: November 26
    End: December 9
    Grade: A
    Daily rate: 485

    Run 4:
    Start: December 10
    End: January 5
    Grade: B
    Daily rate 382


    Etc...

    Thanks a lot!

  2. #2
    Forum Contributor
    Join Date
    08-01-2012
    Location
    Chicago
    MS-Off Ver
    Excel 2010
    Posts
    112

    Re: calculating values over dates

    posting an attachment would be helpful.
    how much of which grade? so a sum of daily rates by grade level?

  3. #3
    Registered User
    Join Date
    06-09-2011
    Location
    North Carolina, USA
    MS-Off Ver
    Excel 2007
    Posts
    13

    Re: calculating values over dates

    Yes, a sum of daily rates by grade level that would give me how much of grade A is produced in November and how much of grade B. Same thing for December, January, etc.

  4. #4
    Forum Contributor
    Join Date
    08-01-2012
    Location
    Chicago
    MS-Off Ver
    Excel 2010
    Posts
    112

    Re: calculating values over dates

    without an attachment its difficult to see how its layed out.
    but i would suggest something like a sumif table
    Last edited by ajm123456789; 10-15-2012 at 02:07 PM.

  5. #5
    Registered User
    Join Date
    06-09-2011
    Location
    North Carolina, USA
    MS-Off Ver
    Excel 2007
    Posts
    13

    Re: calculating values over dates

    Hi!
    I am trying to populate the monthly volume per grade. Any help?
    Attached Files Attached Files

  6. #6
    Forum Contributor
    Join Date
    08-01-2012
    Location
    Chicago
    MS-Off Ver
    Excel 2010
    Posts
    112

    Re: calculating values over dates

    grade(1).xlsx
    the equation changes when the year changes

  7. #7
    Forum Contributor
    Join Date
    08-01-2012
    Location
    Chicago
    MS-Off Ver
    Excel 2010
    Posts
    112

    Re: calculating values over dates

    u could use a row where the year appears and have the formula reference that. then you can hide the formula. This way you will not have the manually change the equation every time the year changes.

  8. #8
    Registered User
    Join Date
    06-09-2011
    Location
    North Carolina, USA
    MS-Off Ver
    Excel 2007
    Posts
    13

    Re: calculating values over dates

    The problem is that when a run starts in one month and finishes another month, your solution gives all the volume to one month, without splitting. i would like to see the split.

  9. #9
    Forum Contributor
    Join Date
    08-01-2012
    Location
    Chicago
    MS-Off Ver
    Excel 2010
    Posts
    112

    Re: calculating values over dates

    and how would you like it split. (daily rate / number of days from start to end) * number of days in month?
    you're not being very helpful neocuproine. this is not a mind reading forum

  10. #10
    Registered User
    Join Date
    06-09-2011
    Location
    North Carolina, USA
    MS-Off Ver
    Excel 2007
    Posts
    13

    Re: calculating values over dates

    I appreciate your help and I apologize if I am not clear enough.
    Yes, what you are suggesting makes sense: if the run starts on November 15 until December 10 for grade A at a daily rate of 320, then it would be 15 days @ 320 = 4800 for November on A and 3200 for A in December. But if A starts again on December 28 until January 12 at a daily rate of 500, then the new December A total would be 3200 + (4 * 500) = 5200.

    Hope it helps

  11. #11
    Forum Contributor
    Join Date
    08-01-2012
    Location
    Chicago
    MS-Off Ver
    Excel 2010
    Posts
    112

    Re: calculating values over dates

    Attachment 187079
    do a few spot checks to make sure its correct

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1