Hi there,
Please help me with a formula for the situation below.
Work week is from Sunday to Thursday (8.30 am to 5.30 pm)
Example:
StartDate: 01/06/2010 10:00 AM in A1
EndDate: 09/06/2010 04:00 PM in B1
StartTime: 08:30 am in A4
EndTime: 05:30 pm in A5
I need to calculate working hours (in decimal format e.g 30.75 hours) between the above start and end date/time considering a work day is of 9 hours and non-working days are Fridays & Saturdays along with any HolidayList.