Thank you. I do use the analysis toolpak.
What if I'm using the following format? I need to fill-in, producing 2 units
per production date (workdays only, and keeping within the specified month).
I can calculate the interval, but can't get my head around how to change the
production date...?
Unit #___ProdtntMth___Category__Days/Mth__Units/Mth__Interval__ProdtnDate
ac02036__5/1/06_____AC_____31_____5_____12_____5/1/06
ac02035__5/1/06_____AC_____31_____5_____12_____5/1/06
ac02034__5/1/06_____AC_____31_____5_____12_____5/13/06
ac02033__5/1/06_____AC_____31_____5_____12_____5/13/06
ac02032__5/1/06_____AC_____31_____5_____12_____5/25/06
ac02031__6/1/06_____AC_____30_____3_____20_____
ac02028__6/1/06_____AC_____30_____3_____20_____
ac02027__6/1/06_____AC_____30_____3_____20_____
ap02059__3/1/06_____AC_____31_____4_____14_____
ap02061__3/1/06_____AC_____31_____4_____14_____
ap02062__3/1/06_____AC_____31_____4_____14_____
ap02063__3/1/06_____AC_____31_____4_____14_____
ap02088__4/1/06_____AC_____30_____6_____10_____
ap02087__4/1/06_____AC_____30_____6_____10_____
ap02086__4/1/06_____AC_____30_____6_____10_____
ap02085__4/1/06_____AC_____30_____6_____10_____
ap02064__4/1/06_____AC_____30_____6_____10_____
ap01033__4/1/06_____AC_____30_____6_____10_____
ap02080__5/1/06_____AC_____31_____5_____12_____
ap02079__5/1/06_____AC_____31_____5_____12_____
ap02078__5/1/06_____AC_____31_____5_____12_____
ap02065__5/1/06_____AC_____31_____5_____12_____
ap02066__5/1/06_____AC_____31_____5_____12_____
"Gary L Brown" wrote:
> Forgot to mention that the Analysis Toolpak addin needs to be available. If
> you're not sure...
>
> Tools>Addins...
> If 'Analysis Toolpak' is not checked, check it.
> Select OK.
>
> HTH,
> --
> Gary Brown
> gary_brown@ge_NOSPAM.com
> If this post was helpful, please click the ''Yes'' button next to ''Was this
> Post Helpfull to you?''.
>
>
> "Gary L Brown" wrote:
>
> > Assume:
> >
> > Cell A1 = # units produced evenly scheduled throughout the month
> > Cell B1 = # of units
> > Cell C1 = # of schedule dates
> > Cell D1 = # of workdays in between schedules
> > Cell E1 = 1st Day of Month
> > Cell F1 = Schedule 1
> > Cell G1 = Schedule 2
> > Cell H1 = Schedule 3
> > Cell I1 = Schedule 4
> > Cell J1 = Schedule 5
> > Cell K1 = Schedule 6
> > Cell L1 = Schedule 7
> > Cell M1 = Schedule 8
> > Cell N1 = Schedule 9
> > Cell O1 = Schedule 10
> >
> > Cell A2 = YOUR INPUT - EXAMPLE: 2
> > Cell B2 = YOUR INPUT - EXAMPLE: 5
> > Cell C2 = =ROUNDUP(B2/A2,0)
> > Cell D2 = =ROUND(NETWORKDAYS(EOMONTH(E2,-1)+1,EOMONTH(E2,0))/C2,0)
> > Cell E2 = YOUR INPUT - EXAMPLE: 01-Mar-2006
> > Cell F2 = =IF(COUNTA($F1:F1)>$C2,"",WORKDAY(E2-1,$D2))
> > copy Cell F2 over to G2:O2
> >
> > Using the example information above...
> > Cell A2 = 2
> > Cell B2 = 5
> > Cell C2 = 3
> > Cell D2 = 8
> > Cell E2 = 01-Mar-2006
> > Cell F2 = 10-Mar-2006
> > Cell G2 = 21-Mar-2006
> > Cell H2 = 30-Mar-2006
> > Cell I2 =
> > Cell J2 =
> > Cell K2 =
> > Cell L2 =
> > Cell M2 =
> > Cell N2 =
> > Cell O2 =
> >
> > HTH,
> > --
> > Gary Brown
> > gary_brown@ge_NOSPAM.com
> > If this post was helpful, please click the ''Yes'' button next to ''Was this
> > Post Helpfull to you?''.
> >
> >
> > "jct" wrote:
> >
> > > How can I calculate the following:
> > >
> > > # units / mth, 2 units produced evenly scheduled throughout the month, only
> > > on weekdays
> > >
> > > 6 units - Jan (resulting in 3 schedule dates)
> > > 4 units - Feb (resulting in 2 schedule dates)
> > > 5 units - Mar (resulting in 3 schedule dates)
> > >
> > > How would the calculation be modified to schedule 1 unit evenly throughout
> > > the month?
> > >
> > > Thank you in advance,
> > > Janice