Hello All!
I am currently working on a project involved in the fabrication and manufacturing of Tanks and am assigned to track the activities involved using excel.
I have attached an excel sheet which contains estimations of Man-hours required to build each component. I wish to know if there is a way to convert the man-hours allocated to actual hours work down into % percentage progress of work done on each component.
What formula should I be using to get % of work completion based on man-hours allocated to actual man-hours?