Hi,
I have a table of planned dates with corresponding planned % values.
I am trying to get a formula which will help calculate a forecast completion date, given the status at a particular date.
Explained well in attached sheet.
Thanks in advance
Hi,
I have a table of planned dates with corresponding planned % values.
I am trying to get a formula which will help calculate a forecast completion date, given the status at a particular date.
Explained well in attached sheet.
Thanks in advance
Hi
Use for delays:
Formula:
Please Login or Register to view this content.
Hi Jose Augusto,
Its giving value 52.68 whereas delay is actually 21 days
Hi
Sorry for the mistake
Formula:
Please Login or Register to view this content.
(No $F$3% but $F$3)
Hi Jose Augusto,
When I change the date, its giving error
Hi
What date are you using?
Hi
The formula I provided earlier does not work correctly. Try this
Formula:
Please Login or Register to view this content.
See the file
There are currently 1 users browsing this thread. (0 members and 1 guests)
Bookmarks