I am not sure why 2 is classed as SLA Met -- given this spans the entire weekend this exceeds 12 hours (total duration is 18:11)
The attached has one approach but it's pretty "ugly" / brute force, and I'm sure someone will have a more succinct alternative that's beyond me at this point...
there used to be some folk on this board who were amazing at this type of calc - but they don't seem to be around any more...
the above basically multiplies each day by either 9 or 12 hours depending on weekday (i.e. 9 for w/e), and then subtracts from that result the hours not worked on both start & end date {relative to respective weekday hours}.
note: I've attached a file to illustrate, this should auto translate the above to reflect your own locale (delimiters etc)