Hi,
I have been struggling with this problem all day and I was wondering if anyone on here may be able to help me please. We are running a factory with two shifts 06:00 until 16:00 and then 20:00 until 06:00 Monday to Thursday. When I know the start date and time of a production run and I know how many hours the product will run for I want to calculate the finish time but taking into account the period each day between 16:00 and 20:00 when there is no production. If there wasn't a four hour gap each day I could do it quite easily but this four hours is causing me hours and hours of pain, please can anyone help?
Product Run Time (hrs) Start Date and Time End Date and Time
X 4 Mon 13 Aug 18 10:45 = Start Date and Time + Run Time
Y 13 = Previous End Date and Time = So on and so on.
Z 22
A 8
B 3
C 4
D 2