I'm trying to set up a field using the following formula =IF(V3="Yes","COMPLETE",IF(D3="","",IF(D3>1/1/17,=(WORKDAY (D3+10))). I can get it to work if I just use the DATE function and add 3 days, but I want it to return a workday date. CAn this be done? Thank you in advance.