Try
=NETWORKDAYS.INTL(A1,A2,1,Holidays)+NETWORKDAYS.INTL(A2,A2,1,Holidays)*(MOD(A2,1)-1)-NETWORKDAYS.INTL(A1,A1,1,Holidays)*MOD(A1,1)
Try
=NETWORKDAYS.INTL(A1,A2,1,Holidays)+NETWORKDAYS.INTL(A2,A2,1,Holidays)*(MOD(A2,1)-1)-NETWORKDAYS.INTL(A1,A1,1,Holidays)*MOD(A1,1)
There are currently 1 users browsing this thread. (0 members and 1 guests)