Network days between dates, less a half day marker

Threaded View

  1. #1
    Forum Contributor
    Join Date
    02-14-2012
    Location
    Warrington
    MS-Off Ver
    Excel 365
    Posts
    497

    Network days between dates, less a half day marker

    Need to work out the working days (Mon-Fri), excluding bank holidays, between the start and end dates in columns A + B, by month in columns E-P.

    This all works fine with the current formula.

    Change required:

    -Need to deduct 0.5 where there is an x in either the afternoon or morning columns (Denoting half a day, instead of a full day). This can be applied to the first month where the days are split between more than 1 month. E.g. row 5 would be 0.5 days in Mar and 1 day in Apr, instead of 1 day in Mar and 1 day in Apr.

    Can do it with a few ifs but thought there maybe a nice short and fancy way
    Attached Files Attached Files

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. [SOLVED] Count 6 working days (excluding Sunday, Holidays & half days)
    By eve_star1 in forum Excel Formulas & Functions
    Replies: 6
    Last Post: 01-29-2015, 08:00 AM
  2. counting half days
    By chanman008 in forum Excel Formulas & Functions
    Replies: 7
    Last Post: 09-11-2014, 03:23 PM
  3. Replies: 8
    Last Post: 02-08-2013, 04:29 AM
  4. [SOLVED] Subtracting Hold Days from Network Days Formula
    By david1987 in forum Excel Formulas & Functions
    Replies: 1
    Last Post: 10-17-2012, 08:30 AM
  5. Replies: 5
    Last Post: 12-15-2011, 11:16 AM
  6. Replies: 5
    Last Post: 04-25-2008, 03:35 PM
  7. Excel Sick Days / Half Days
    By Pixie_1 in forum Excel General
    Replies: 6
    Last Post: 02-28-2007, 08:28 AM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1