Hi Everyone,
I need a formula to help with my companies delivery dates.
The way we work it out is.
The job is put into production and takes a set amount of days to be completed,
Kitchens= 6 days
Bedrooms= 5 Days
Bathrooms= 12 Days
on the last day of the days it arrives in the warehouse,
from here we calculate the delivery date.
2 days for our north deliveries
3 days for our south deliveries
here is an example (kitchen Called of date 14/01/2015 arrives in the warehouse 21/01/2015, is loaded on the 22/01/2015 can be delivered north on the 23/01/2015 or south on the 26/01/2015)
currently this is worked out in our heads which causes a few problems.
What I am struggling with is weekends and adding days where we don't have production. As I will need a box to add days where production is closed.
Any help will be greatly appreciated.
Kind Regards,
Mike