    Add days between start date and end date

    Hello,

    I need help on date formula. What I am trying to accomplish is, to add days from the start date (daily) and to stop adding at the end date.

    Example:
    (Column A) Start Date: 1/9/13
    (Column B) End Date: 1/8/14

    Thank you,
    dache416

  2. #2
    Forum Moderator alansidman's Avatar
    Join Date
    02-02-2010
    Location
    Steamboat Springs, CO
    MS-Off Ver
    MS Office 365 insider Version 2504 Win 11
    Posts
    24,705

    Re: Add days between start date and end date

    Attach a sample workbook. Make sure there is just enough data to demonstrate your need. Include a BEFORE sheet and an AFTER sheet in the workbook if needed to show the process you're trying to complete or automate. Make sure your desired results are shown, mock them up manually if necessary.

    Remember to desensitize the data.

    Click on GO ADVANCED and use the paperclip icon to open the upload window.

    View Pic
    Alan עַם יִשְׂרָאֵל חַי


    Change an Ugly Report with Power Query
    Database Normalization
    Complete Guide to Power Query
    Man's Mind Stretched to New Dimensions Never Returns to Its Original Form

  3. #3
    Forum Guru Pete_UK's Avatar
    Join Date
    12-31-2011
    Location
    Warrington, England
    MS-Off Ver
    Office 2019 (still learning)
    Posts
    25,411

    Re: Add days between start date and end date

    Try this:

    =B1-A1

    Format the cell as General or as a Number. You may need to add 1 at the end of the formula if you want those dates to be inclusive.

    Hope this helps.

    Pete

  4. #4
    Registered User
    Join Date
    05-05-2014
    Location
    Voorheesville, NY
    MS-Off Ver
    Excel 2007
    Posts
    77

    Re: Add days between start date and end date

    The attached spreadsheet shows what I am trying to accomplish. The formula currently in used continuously adds days indefinitely without stopping at the end date. I tried playing with the formula to no avail.

    Any help, is greatly appreciated

    dache
    Attached Files Attached Files

  5. #5
    Forum Guru Pete_UK's Avatar
    Join Date
    12-31-2011
    Location
    Warrington, England
    MS-Off Ver
    Office 2019 (still learning)
    Posts
    25,411

    Re: Add days between start date and end date

    Put this in A5:

    =IF(B$1="","",B$1)

    and this in A6:

    =IF(OR(B$2="",A5=""),"",IF(A5+1>B$2,"",A5+1))

    Copy the formula in A6 down as far as you need to (until you start to get blanks).

    Hope this helps.

    Pete

  6. #6
    Registered User
    Join Date
    05-05-2014
    Location
    Voorheesville, NY
    MS-Off Ver
    Excel 2007
    Posts
    77

    Re: Add days between start date and end date

    Thank you very much Pete

  7. #7
    Forum Guru Pete_UK's Avatar
    Join Date
    12-31-2011
    Location
    Warrington, England
    MS-Off Ver
    Office 2019 (still learning)
    Posts
    25,411

    Re: Add days between start date and end date

    You're welcome - thanks for the rep.

    If that takes care of your original question, please select Thread Tools from the menu above your first post and mark this thread as SOLVED.

    Pete

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Replies: 10
    Last Post: 02-29-2024, 08:55 AM
  2. Replies: 1
    Last Post: 05-26-2014, 03:46 AM
  3. Calculate End Date Using Start Date and No. of Days excluding specific days.
    By SinusxCosinusx in forum Excel Programming / VBA / Macros
    Replies: 3
    Last Post: 11-22-2013, 05:48 AM
  4. [SOLVED] Calculate END DATE based on START DATE & No of working days
    By prashantha in forum Excel Formulas & Functions
    Replies: 6
    Last Post: 11-20-2013, 07:22 AM
  5. [SOLVED] Find date using start date and number of network days
    By v!ctor in forum Excel General
    Replies: 4
    Last Post: 07-06-2012, 05:27 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1