I would like to create a Today Line that will start from the to column date right down to the last entry of the activities..
How do i create this line. Do i again use conditional formatting?
thanks
I would like to create a Today Line that will start from the to column date right down to the last entry of the activities..
How do i create this line. Do i again use conditional formatting?
thanks
You have column headers with dates in steps of 7 days. Where do you expect to see a "date line"?
You can use conditional formatting to highlight a column if it is between two dates, e.g. between today() and today()-7 or between today() and today()+7
Your data does not readily present where to put the highlight. Please clarify.
Hi
Apologies for not being clear. I would like a today date line (e.g. line in MS projects) to show todays date in the project plan. This will then highlight todays date and also sub-tasks that are behind (not completed).
Ive attached a better example#
Thanks