Help pls, am try to create gantt chart for my project time line but now am struck with 1 activity have 2 duration period e.g
Phase 1 start date 1st Jan 2017 duration 58days so end date will 28 Feb 2017 and other strat date is 30 Aug 2017 duration date is 90 so end date will 30 Nov 2017.
I should have 2 bar chart for phase 1 but I don't know how to do. so you help much appreciate
Thanks in advance