    Excel Chart - TimeLine

    Hello guys.
    First of all, lovely forum i found here

    I'm creating a Gantt Chart, but i'm having some difficulties to put the axis with timeline of one day: 0H - 24H
    In this momment the axis contains only 0H 0H 0H (...)

    Testing GANTT.xlsx

    Can help me please?

    Thank you!
    Attached Files Attached Files

  2. #2
    Forum Guru
    Join Date
    04-13-2005
    Location
    North America
    MS-Off Ver
    2002/XP, 2007, 2024
    Posts
    16,373

    Re: Excel Chart - TimeLine

    I am not certain what you want your final chart to look like. The first thing I did was select the horizontal axis -> format axis then see what the axis limits are set to. I notice that it is set to extend from 21 days to 42 days (a total elapsed time of 21 days), but the data appear to only extend over less than 2 days. I left the minimum to fixed at 21, then selected auto for the axis maximum. I also set the major unit to 0.125 (1/8th of a day or 3 hours) to better see how the data was spread out over those 2 days.

    I don't expect that is all of what you are looking for, but it might help you see what the chart is charting and see how to adapt it to what you want. It also might help you explain to us in more detail exactly what you are looking for.
    Quote Originally Posted by shg
    Mathematics is the native language of the natural world. Just trying to become literate.

  3. #3
    Registered User
    Join Date
    02-09-2017
    Location
    Portugal
    MS-Off Ver
    2010
    Posts
    10

    Re: Excel Chart - TimeLine

    Thanks mate!

    I did some changes and i think now it's like i want:

    Testing GANTT_JMR.xlsx


    My intent is to put a timeline of 24 hours of only 1 day in X axis.

  4. #4
    Forum Guru
    Join Date
    04-13-2005
    Location
    North America
    MS-Off Ver
    2002/XP, 2007, 2024
    Posts
    16,373

    Re: Excel Chart - TimeLine

    If that resolves your question, you can mark the thread as SOLVED to indicate. (Thread tools -> Mark as solved)
    My intent is to put a timeline of 24 hours of only 1 day in X axis.
    It appears that your current data span over about 2 days rather than just 1 day. It appears to me that, in order to compress it into one day, you will need to change the data/formulas in the spreadsheet in order to get the stacked bar/Gantt chart to fit within 1 day.

  5. #5
    Registered User
    Join Date
    02-09-2017
    Location
    Portugal
    MS-Off Ver
    2010
    Posts
    10

    Re: Excel Chart - TimeLine

    Thank you mate!

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Multiple questions about Excel project timeline, % formulas, refresh timeline
    By Please Help in forum Excel Formulas & Functions
    Replies: 2
    Last Post: 07-27-2016, 07:13 PM
  2. Yearly Timeline Chart for Excel
    By CCNY29 in forum Excel Charting & Pivots
    Replies: 2
    Last Post: 04-18-2016, 01:21 PM
  3. Replies: 1
    Last Post: 08-28-2015, 09:35 AM
  4. [SOLVED] Excel Chart - Text on a Timeline
    By jdbrownwv in forum Excel General
    Replies: 6
    Last Post: 06-21-2012, 07:50 AM
  5. Excel Autofill/Timeline/Gantt Chart
    By Rivendair in forum Excel Programming / VBA / Macros
    Replies: 0
    Last Post: 07-12-2011, 09:43 PM
  6. Excel chart - simultaneous timeline
    By lightsandsirens in forum Excel General
    Replies: 0
    Last Post: 03-16-2011, 02:11 AM
  7. Import MS Project timeline (Grantt Chart) to Excel
    By 102pdpcantho in forum Excel General
    Replies: 1
    Last Post: 03-10-2011, 11:57 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1